Ashtart
field
A side track of ASH 77GH take place from
September 5th to October 11th 2007 to drill a horizontal leg.
The well flowed initially 1100 BOPD then decreased to 300 BOPD
end of November 2007.
Side track campaign of ASH 42, 49 and 50 is planned during the
second and third quarter 2008.
Ashtart revamp project has started in April 2005. This involves
the upgrade of Ashtart topsides facilities. Project execution
for EPCI was sanctioned by partners. Long lead packages are
under procurement stages. Tender for EPCI phase is prepared to
be launched in January 2008. Tender for consultancy services for
technical support was floated. EPCI tender for pipelaying is
under preparation.
The field is currently producing around 10 000 BOPD.
Sidi
El Kilani field
Sidi Kilani 12 spud on August
10th, 2007, reached TD of 1658 m on October 27th 2007. The well is producing 10
BOPD.
The field is currently producing around 1 400 BOPD.
Cercina
field
Activation of Cercina South 1 and Cercina
13 wells with ESP is planned for the 1st quarter 2008.
A 3D seismic acquisition over Cercina field is completed by CGG. Processing and
interpretation is ongoing under OMV and ETAP supervision.
The field is currently producing around 2 000 BOPD.
El
Hajeb & Guebiba
fields
Installation of an ESP on GUE 10A well during the first
week of 2008. The well is producing 2250 BOPD.
Installation of an ESP on GUE 5 well was completed in
November 2nd 2007. The well is producing 560 BOPD.
GUE 9 well was activated by jet pumping system on August
2007 and is producing 1700 BOPD.
Installation of a sucker rod pump on EHJ 7 well in November
25th 2007. The well is producing 240 BOPD.
These fields are currently producing around 7 000 BOPD.
Makhrouga, Laarich
& Debbech
fields (MLD)
A new development well Larich SE-2 was drilled from June 5th
to July 29th. The well is producing 730 BOPD.
These fields are currently producing around 3 000 BOPD.
Ezzaouia
field
Drilling of two development wells EZZ 17 and 18 is planned
for the 2nd quarter 2008.
The field is currently producing around 1 100 BOPD.
Adam,
Hawa, Dalia, Nour, Janet, Karma and Iklil fields
Drilling of a second development well Nour 2 was finalised in
April 2007. The well is flowing 600 BOPD from the Acacus.
A reservoir simulation study for Adam and Hawa fields to
implement new wells is ongoing.
These fields are currently producing around 18 500 BOPD.
Oued
Zar & Hammouda fields
Drilling of a new development well HMD 7 reached TD in May 2007. The well flowed
600 BOPD.
A water injection study for the main oil layers of Oued Zar and Hammouda fields
is ongoing.
These fields are currently producing around 5 000 BOPD.
Franig
fields
Drilling of a new development well FNG 5 started in December 2007.
The field is currently producing around 2 000 BOPD.
Sabria
fields
Drilling of a multilateral development well SAB 11 reached TD in May 2007.
Production started end of June 2007. The well is flowing 600 BOPD from the
Acacus.
The field is currently producing around 900 BOPD.
 |
CONCESSIONS
UNDER DEVELOPMENT
|
 |
Chergui
field
The development of Chergui field consists of the gas
treatment and compression facilities (CPF) to be installed in Kerkennah Island.
The treated gas will be transported through a 60 km of 8" pipeline to the STEG
24" pipeline in Ain Turkia, north of Sfax.
All the onshore pipelines are installed. The offshore installation works is
under completion.
CPF contract:
Engineering activities are finalized by PETROFAC, partner with ETAP. The CPF
installation is under completion. Plant commissioning has started. First gas is
planned 1st quarter 2009.
Hasdrubal field
Hasdrubal field is located Offshore Gulf of Hammamet, BG in operator (50%) with
ETAP (50%)
The development consists of an offshore Normally Unmanned Installation (NUI) to
house 4 gas producing wells and 2 oil producing wells and an 18” pipeline (117
Km) connecting the offshore installations to the onshore gas treatment plant.
The gas treatment plant will process 120 MMSCFD of gas to produce commercial gas,
stabilized condensate and LPG.
Drilling has commenced for phase 1 (4 wells) on December 2007. Phase 2 will
start mid 2009.
First gas is expected by 1st quarter 2009.
Development drilling :
|
Concession
|
Operator |
Well |
Rig |
Spud/End
Dates |
Depth (MD)
|
Results |
|
ADAM |
ENI |
Nour 2 |
Pergemine |
24/01/2007
28/03/2007 |
3625 m |
Flowed 600 BOPD from Acacus |
|
OUED ZAR |
ENI |
Hamouda 7 |
CTF 06 |
07/04/2007
30/05/2007 |
3550 m |
Flowed 800 BOPD from Acacus |
|
ASHTART |
SEREPT |
ASH 77 GH |
CTF 05 |
30/04/2007 16/07/2007 |
3457 m |
Temporarily abandoned |
|
ASHTART |
SEREPT |
ASH 77 GH
ST |
CTF 05 |
05/09/2007 11/10/2007 |
3395 m |
Flowed initially 1100 BOPD from El
Guéria |
|
MLD |
SODEPS |
LAARICH SE 2 |
CTF 04 |
05/06/2007
31/07/2007 |
4217 m |
Flowed initially 1100 BOPD from El
Guéria |
|
SIDI EL KILANI |
CTKCP |
SLK 12 |
GW DC 69 |
10/08/2007
23/10/2007 |
1835 m |
Flowed 10 BOPD from the Abiod |
|
HASDRUBAL |
BG |
HASDRUBAL
A1 |
CFT 04
Oilwell 2000 |
05/12/2007
- |
3821 m |
Drilling ongoing |
|
FRANIG |
FERENCO |
FRANIG 5 |
GWDC 69 |
15/12/2007
- |
3990 m |
Drilling ongoing |